Mr. Quarshigah (R) briefing Mr. Bani (L) |
Contractors working on the
Ho -Adidome trunk road in the Volta region are yet to receive monies from the
ministry of finance to enable them complete work on the road, three weeks after
President Mahama announced the release of funds to that effect during a day’s
inspection tour of the road.
This was disclosed on
Sunday to the Chief of Staff Mr. Prosper Douglas Bani when paid a day’s working
visit to the region to ascertain the progress of work on the road since the
president’s last visit.
The resident engineer in
charge of the project, Mr. Divine Quarshigah, told the chief of staff and his entourage
that, though some culvert works are ongoing on the road, work is progressing at
slow pace due to the delays in the release of funds to the contractors, Ussuya
Ghana Ltd, PMC and Jani-CORP enable them
fully mobilise back to site.
‘The contractors have not received
any payment after the president came’ he said and explained further that his
checks as of last Friday revealed that the payment process has left the Ghana
Highway authority to the finance ministry.
The delay in the release of
the monies to contractors according to the resident engineer is one the major
challenges hampering the speedy completion of the 48km road, with the second
challenge being heavy rains which disrupt work because of the porous nature of
some portions of the area.